Federal Task Force on the Boston Central Artery Tunnel Project

Review of Project Oversight and Costs

The Central Artery/Tunnel (CA/T) Project in Boston, MA, is the largest federally funded public works project in recent history, involving the reconstruction of I-93 and the extension of I-90. The CA/T Project is approx, 7.5 miles long and includes approx. 160 lane-miles of new and reconstructed highway. The majority of the CA/T Project is below ground. More Fed. funding ¿ $5.8 billion and growing ¿ has been allocated to the CA/T Project than to any other construction project of its kind. Contents of this review conducted in 2000: Objectives: Assess the Oversight Process; Review the Management Structure; Validate the $1.4 Billion Potential Cost Overrun; Identify Potential New Cost Indicators; Identify Potential Cost Saving Measures. Charts and tables.

Although the Plan indicates the State is committed to a balanced statewide
transportation program, the basis for this commitment appears to be State internal
policy without a binding agreement. This commitment has two parts. First, the
State ...